7-hr mega block in Navi Mumbai for Metro work

NAVI MUMBAI: Cidco has been granted permission by way of the Central Railway to hold out a seven-hour mega block Sunday for shifting of the truss over the Diva-Panvel line that is a hectic Konkan and southern path. This is the longest of all of the 9 blocks.

The truss is to glue the 9th and tenth stations of Amandoot and Taloja at the ongoing Metro line I work for providing connectivity from Belapur to Pendhar spanning a distance of 11.1km and 11 stations.


Line I is the first segment of the overall four lines for town to connect with the impending new global airport.


The truss has to be moved with winch and pulley to a distance of 130 meter from the assembling level.


Cidco stated the truss has been moved 21 meters to this point within the closing three blocks, so the weekend block will mean the truss could have moved 78 meters. The fifth block sanction of three hours has additionally been bought for Tuesday within the coming week.