Avinashi Flyover project report to be ready within 2 months

COIMBATORE: Construction of a flyover on one of the most congested roads in the city, Avinashi Road, is anticipated to begin quickly, with the state highways department on the brink of put up a detailed mission file (DPR) inside two months.
In an try to cut back site visitors congestion in the heart of the city and to lend a hand commuters reach the airport without being stuck in site visitors snarls, the state executive had proposed the 8.5-kilometre flyover from Uppilipalayam Junction to SITRA-Kalapatti Junction in 2015. The work to arrange the DPR had commenced in September 2017.

“The department has already completed site visitors and topographic survey of the road. But, we had to acquire soil samples from about 170 locations alongside the Avinashi Road to check the bearing capability of soil,” a highways department reliable mentioned.

While soil samples from greater than 130 places till the Airport Junction have been despatched for checking out, the ones from the remaining places could be completed inside a week, the reliable mentioned. The samples are tested at the Government College of Technology (GCT) on Thadagam Road.

The check effects will probably be despatched to the consultant for designing. “An estimate could be ready in line with the design and all of the process is anticipated to be completed inside two months. Earlier, the deadline to put up the DPR was once fastened for this March. But we extended it till June due to the prevailing site visitors congestion on the road,” the reliable mentioned. As a end result, the process that commenced in November, is yet to finish.


The designing work will start from subsequent week, the reliable mentioned. “Based on the soil checking out file, factors like peak and width of the pillars, collection of pillars, sort and intensity of the foundation could be determined. The plan is to have ramps to and from the flyover at about 4 junctions. We may even come to a decision on the location for provider roads and ramps,” he advised TOI.


“For now, we have created a tentative design, approximately figuring out the grid and length of the ramps and the place to dig for pillars,” the reliable added.


The value estimation of the mission is anticipated to be over Rs 950crore. The state executive has allotted about Rs three.5 crores for the preparation of DPR.